Chapter 5 - Stakeholder Coordination: Difference between revisions
No edit summary |
No edit summary |
||
| Line 1: | Line 1: | ||
<!--Chapter | <!--Chapter 3 HTML--> | ||
< | <div class="noautonum cFloat">__TOC__</div> | ||
<p>Project | <h1> | ||
Chapter 3 - Project Initiation | |||
</h1> | |||
<p> | |||
After a project is originated in accordance with one of the mechanisms described in [[Chapter 2 - Project Origination and Planning|Chapter 2]], it is assigned to a section within DelDOT for further development. This stage in the project development process is generally referred to as project initiation. This chapter serves to document the numerous tasks that a section must perform as part of the project initiation process once assigned a project. Project initiation is a relatively short phase in the project development process but serves an essential role of establishing an initial project baseline to follow through the remainder of the project development process. The activities described within this chapter can be performed in various orders depending on the complexity of a project. For instance, it may be preferrable to perform a detailed scoping and alternatives analysis prior to setting a project schedule while on other projects it may be preferable to account for the scoping and alternatives analysis within the initial project schedule submitted with the Project Number Request. | |||
</p> | |||
<div class="tab"> <!--h2--> | <div class="tab"> <!--h2--> | ||
<h2> | <h2> | ||
<p> | 3.1 Establishment of the Design Team | ||
</h2> | |||
<p> | |||
The section assigned to develop a project should establish a design team comprised of a Project Manager and technical design staff as soon as practical. Collectively, the design team is charged with guiding a project through DelDOT’s project development process outlined within this manual. The Project Manager’s role in the project development process is to coordinate technical design staff assignments and ensure that all work is being completed at the correct performance level, on time, and within budget and scope. The technical design staff’s role in the project development process is to perform the tasks assigned to them by the Project Manager in accordance with this manual as well as other DelDOT standard and guidance documents. The Project Manager should evaluate the composition of the team at regular intervals throughout the project development process to ensure on-time and on-budget delivery. | |||
</p> | |||
<p> | |||
In general, projects can either be developed through in-house staff or can be developed in-whole or in-part by contracted consultant staff through professional service agreements. The Project Manager should consider multiple factors when establishing the design team, including but not limited to, the following: | |||
</p> | |||
<ul> | |||
<li> | |||
Availability of in-house staff, | |||
</li> | |||
<li> | |||
Expertise and experience required to perform project related tasks, | |||
</li> | |||
<li> | |||
Desired implementation schedule, and | |||
</li> | |||
<li> | |||
Available funding. | |||
</li> | |||
</ul> | |||
<p> | |||
The procurement and subsequent management of professional services is further discussed in [[Chapter 3 - Project Initiation#3.4 Professional Services|Section 3.4]] of this manual. | |||
</p> | |||
<div class="tab"> <!--h3--> | <div class="tab"> <!--h3--> | ||
<h3> | <h3> | ||
3.1.1 Support Groups | |||
</h3> | </h3> | ||
<p> | <p> | ||
The | The design team’s efforts are supplemented by Support Groups throughout DelDOT. Support Groups typically oversee a particular area of the of the project development process and perform ancillary tasks to deliver a project. Support Groups are relied upon by DelDOT as subject matter experts within their field due to their focus and expertise on a particular subject matter within the project development process. The process established in this manual is intended to leverage the expertise and experience of DelDOT’s of subject matter experts in order to develop complete, accurate, and thorough project deliverables which meet the applicable state and federal requirements. Coordination with subject matter experts is typically triggered by milestone submittals which are discussed in more detail in Section 6.3; however, communication and coordination with DelDOT subject matter experts should occur fluidly throughout the project development process as needs arise. Early and consistent communication throughout the project development process will promote informed decision-making, reduce duplicated efforts amongst staff, and allow early identification and subsequent remediation of challenges that could jeopardize project delivery. | ||
</p> | </p> | ||
</div> <!-- | </div> <!--end of h3--> | ||
<h2> | <h2> | ||
3.2 Project Baselining | |||
</h2> | </h2> | ||
<p> | <p> | ||
Project baselining is the term assigned to the task of evaluating a project’s specific conditions, parameters, and other associated constraints to determine an estimated project schedule and budget. A project is baselined during the project initiation phase and will typically be re-baselined several times throughout the full project development process. The design team should collaborate with support sections as needed while performing this task to ensure the development of accurate project baselines. Accurate project baselining is essential to the development of a fiscally constrained program to make efficient use of transportation funds. | |||
</p> | </p> | ||
<div class="tab"> <!--h3--> | <div class="tab"> <!--h3--> | ||
<h3> | <h3> | ||
3.2.1 Initial Project Baselining | |||
</h3> | </h3> | ||
<p> | <p> | ||
Once assigned a project, the assigned section must review the project’s proposed scope and any associated planning and study level documents to create a project schedule, budget, and an initial environmental evaluation. In cases where the project scope and goals are unclear, additional project scoping and alternatives analysis may be performed before establishing the project’s initial baseline. Some projects may come with a previously developed schedule and budget depending upon the program generating the project; in these cases, the design team should evaluate the validity of any previously developed schedules and budgets before formally committing to any previously developed project baselines. | |||
</p> | |||
<p> | |||
The design team should evaluate the project at this initial baselining stage to determine if an alternative project delivery or alternative contracting method should be pursued for the project. Additional information on the available contracting and project delivery methods are provided in Section 6.1. | |||
</p> | </p> | ||
<p> | |||
At a minimum, the assigned section should make a concerted project scoping effort to identify the key project stakeholders as well as other specific conditions or parameters that could affect the project development process while developing the initial baseline. Additional information on project scoping is included in [[Chapter 3 - Project Initiation#3.6 Project Scoping|Section 3.6]]. | |||
</p> | |||
<div class="tab"> <!--h4--> | <div class="tab"> <!--h4--> | ||
<h4> | <h4> | ||
3.2.1.1 Schedule | |||
</h4> | </h4> | ||
<p> | <p> | ||
Project scheduling requires the identification of all necessary work activities, development of work-hour estimates for work activities, and then defining relationships between the work activities to produce the project desired deliverables. The Project Manager is tasked with either verifying a previously developed project schedule or developing a new project development schedule as part of the project initiation process. The initial project development schedule will need to identify the proposed completion month for all milestone project development deliverables. DelDOT’s typical milestone deliverables are discussed in more detail in Section 6.3. The Project Manager is encouraged to use scheduling tools commensurate with the project’s complexity to assist in the development of the initial project schedule. Project scheduling tools can range from a simple Excel spreadsheet to a complex scheduling software that assigns task durations and analyzes critical paths. | |||
</p> | </p> | ||
<p> | <p> | ||
The Project Manager should consider all project specific criteria when developing the initial project schedule. Considerations include, but are not limited to, the following: | |||
</p> | </p> | ||
<ul> | <ul> | ||
<li> | <li> | ||
<li> | The potential use of any contracting methods as discussed in Section 6.1, | ||
<li> | </li> | ||
<li> | |||
Availability of the assigned design team, | |||
</li> | |||
<li> | |||
Experience and associated capability of the assembled design team, | |||
</li> | |||
<li> | |||
Complexity of the project, | |||
</li> | |||
<li> | |||
The number and type of desired milestone submittals and deliverables, | |||
</li> | |||
<li> | |||
Identification of any critical project milestone dates, | |||
</li> | |||
<li> | |||
Time needed for initial site investigation, | |||
</li> | |||
<li> | |||
Time needed for any necessary property acquisitions or trespass/ rail agreements, | |||
</li> | |||
<li> | |||
Time needed to satisfy pertinent environmental requirements (i.e. permitting, wetland mitigation, 106 compliance, NEPA compliance etc.), and | |||
</li> | |||
<li> | |||
Any publicly committed completion timeframes. | |||
</li> | |||
</ul> | </ul> | ||
<h4> | <h4> | ||
2. | 3.2.1.2 Budget | ||
</h4> | </h4> | ||
<p> | <p> | ||
Accurately establishing the budget during the project initiation phase is essential to ensuring a fiscally responsible program and proper project funding. Overestimating the budget will lead to surplus funds being withheld from other infrastructure projects and underestimating the budget could lead to schedule disruptions. A project may be assigned to a section either with or without an already estimated budget depending upon the mechanism generating the project. Whether or not the project is assigned with a pre-estimated budget, the Project Manager and the design team should perform a project cost estimate for the design phase, the right-of-way acquisition, and construction phase which is commensurate with the project’s complexity and overall size. Additional information on cost estimating is included within Section 6.5. In all cases, the project’s budget during this stage in the project development process is to be recorded into the following funding phases: | |||
</p> | </p> | ||
<ul> | <ul> | ||
<li> | <li> | ||
Preliminary Engineering (PE, includes all design related work required to get the project through the advertisement phase), | |||
</li> | |||
<li | <li> | ||
Right-of-Way (RW), and | |||
</li> | |||
<li> | |||
Construction (C, includes any construction contingency, environmental monitoring during construction, railroad construction, traffic construction, reimbursable utility construction, and construction engineering (CE) costs). | |||
</li> | |||
</ul> | |||
</ | |||
</ | |||
<p> | <p> | ||
Items the Project Manager should consider while developing the initial project budget, include but is not limited to, the following: | |||
</p> | </p> | ||
<ul> | <ul> | ||
<li> | <li> | ||
<li> | Professional services required to perform existing site investigation activities discussed in [[Chapter 3 - Project Initiation#3.7 Existing Site Investigation|Section 3.7]], | ||
</li> | |||
<li> | <li> | ||
<li> | Professional services required to perform project design, | ||
<li> | </li> | ||
<li> | |||
Professional services required to perform any ancillary tasks required to deliver a project (i.e. utility coordination, public outreach, environmental permitting etc.), | |||
</li> | |||
<li> | |||
The expected cost of any right-of-way acquisitions that may be required, and | |||
</li> | |||
<li> | |||
The expected cost of all necessary construction and inspection activities. | |||
</li> | |||
</ul> | </ul> | ||
<p> | <p> | ||
Another important item to establish is whether the project will receive federal funding during any project funding phase. This will typically be a joint decision between the design team and the Finance section. It is important to note that once federal funds are used in any funding phase that all previous work performed must meet the pertinent federal requirements. | |||
</p> | </p> | ||
<p> | <p> | ||
Projects assigned with a pre-estimated budget listed in the Capital Transportation Plan CTP may require a funding increase when determined the dedicated funding is insufficient. Additional information on funding increases is provided in [[Chapter 5 -Stakeholder Coordination|Section 5.8.1 (To be added)]]. | |||
</p> | </p> | ||
< | |||
<h4> | |||
3.2.1.3 Initial Environmental Evaluation | |||
</h4> | |||
<p> | <p> | ||
The Federal | The Project Manager should request an initial environmental evaluation from the DelDOT Environmental Stewardship section as part of a project’s initial baselining. The initial environmental evaluation serves to inform the Project Manager and the design team of the environmental coordination related processes and deliverables which will need to be accounted for during their initial baselining effort. To obtain an initial environmental evaluation, the design team will need to complete the Initial Environmental Evaluation Form and submit it to the Environmental Stewardship section. The Environmental Stewardship section will review the information provided by the design team and complete the remainder of the form. The Environmental Stewardship section will submit the completed form back to the design team and will request that the design team attend the next Environmental Stewardship section group meeting, commonly referred to as the ESO meeting, to discuss the content of the initial environmental evaluation as well as the division of work between the design team and the Environmental Stewardship section. The Environmental Stewardship section may contact the Federal Highway Administration (FHWA), or other federal administering agency, in accordance with [https://www.ecfr.gov/current/title-23/part-771 23 CFR 771.111(a)(3)] to obtain advice, insofar as possible, on the probable class of action and related environmental laws and requirements and of the need for specific studies and findings that would normally be developed during the environmental review process. At a minimum, the initial environmental evaluation will provide the following: | ||
</p> | </p> | ||
<table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | <table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | ||
<caption style="caption-side:bottom;font-size: 12px;text-align: left;"></caption> | <caption style="caption-side:bottom;font-size: 12px;text-align: left;"></caption> | ||
<tr> | <tr> | ||
| Line 364: | Line 162: | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td> | <td>Initial Environmental Evaluation Form</td> | ||
</tr> | </tr> | ||
</table> | </table> | ||
<ul> | <ul> | ||
<li> | <li> | ||
<li> | The initial level of environmental documentation and class determination, | ||
<li> | </li> | ||
<li> | |||
Identification of design/project development considerations, including but not limited to, historic properties and structures, archaeological sites, tribal coordination requirements, Section 4(f) and 6(f) properties, wetlands and waterbodies, endangered species, and environmental justice (EJ), | |||
</li> | |||
<li> | |||
An initial public involvement strategy requirement, and | |||
</li> | |||
<li> | |||
Funding needs and task assignments. | |||
</li> | |||
</ul> | </ul> | ||
</div> | |||
<h3> | |||
3.2.2 Project Re-Baselining | |||
</h3> | |||
<p> | |||
A project’s schedule and budget should be re-baselined throughout the project development process to ensure the efficient use of DelDOT resources and to minimize the potential for creating duplicate work products. Projects are typically re-baselined at the milestone submissions described in Section 6.3 and should also be re-baselined when major changes within the project development process occur such as a change in the project team occurs or when previously unanticipated work and coordination efforts become required. Reference should be made to [[Chapter 5 - Stakeholder Coordination|Section 5.8.1 (To be added)] when re-baselining reveals the project has insufficient fund. | |||
</p> | |||
<div class="tab"> <!--h4--> | |||
<h4> | <h4> | ||
2.2. | 3.2.2.1 Re-Baselining at Milestone Submissions | ||
</h4> | </h4> | ||
<table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | <table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | ||
<caption style="caption-side:bottom;font-size: 12px;text-align: left;"></caption> | <caption style="caption-side:bottom;font-size: 12px;text-align: left;"></caption> | ||
<tr> | <tr> | ||
| Line 402: | Line 197: | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>[https://deldot.gov/ | <td>[https://deldot.gov/Business/drc/pdfs/unifier/unifier_training_doc.pdf?cache=1689883703128 Unifier Training Outline]</td> | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>[https://www. | <td>[https://www.youtube.com/watch?v=F5dDS9ITTdU&list=PLZrnWsoNR9WQJ_UVaeKnmpYseK1OlWMQe&index=3 Youtube Tutorial Video]</td> | ||
</tr> | </tr> | ||
</table> | </table> | ||
<p> | <p> | ||
A project’s schedule and budget are to be updated in Unifier at each milestone submission to communicate a project’s current estimated budget and schedule to the rest of DelDOT. The project’s schedule and budget can be estimated using the same considerations as the initial project baselining effort described in [[Chapter 3 - Project Initiation#3.2.1 Initial Project Baselining|Section 3.2.1]]. DelDOT maintains written procedures for updating a project’s information in its [https://deldot.gov/Business/drc/pdfs/unifier/unifier_training_doc.pdf?cache=1689883703128 Unifier Training Outline] and maintains a [https://www.youtube.com/watch?v=F5dDS9ITTdU&list=PLZrnWsoNR9WQJ_UVaeKnmpYseK1OlWMQe&index=3 tutorial video] on the subject on its Youtube channel. | |||
</p> | </p> | ||
<h4> | <h4> | ||
2.2. | 3.2.2.2 Spend Updates | ||
</h4> | </h4> | ||
<p> | <p> | ||
A spend plan that outlines when the project team estimates money will be spent throughout the project development process is created as part of the procedure outlined in [[Chapter 3 - Project Initiation#3.2.1 Initial Project Baselining|Section 3.2.1]]. Periodically throughout the course of the project development process, the Project Manager will review the actual rate of project expenditures compared to the expected expenditure rate in order to evaluate the accuracy of the spend plan. After their review, the Project Manager can recommend that money be moved up in the spend plan or moved back. This practice of reviewing and making recommendations on project funding to the DelDOT Finance team is known as making spend updates. DelDOT sections typically use different spend update intervals based on the amount, complexity, typical schedule, and budget of projects being managed by the section. Conducting spend updates also provides a good opportunity for the Project Manager to review the project’s overall budget to determine if the project will require additional funding or if the project has a surplus amount of funds allotted. | |||
</p> | </p> | ||
</div> <!--End of h4--> | </div> <!--End of h4--> | ||
</div> <!--End of h3--> | |||
<h2> | |||
3.3 Project Number Request | |||
</h2> | |||
<table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | |||
<caption style="caption-side:bottom;font-size: 12px;text-align: left;"></caption> | |||
<tr> | |||
<th colspan="4" style="color:white;background-color:navy;font-weight: bold;text-transform: uppercase;" id="table 1-1">Department Resources</th> | |||
</tr> | |||
<tr> | |||
<td>[https://deldot.gov/Business/drc/index.shtml?dc=unifier Unifier Instructions on the DRC]</td> | |||
</tr> | |||
</table> | |||
<p> | |||
Once the initial project baselining is complete, a New Project Request and subsequent Project Number Request can be performed. DelDOT assigns a state project number and a federal project number, when necessary, to its projects to assist with project identification and tracking. The New Project Request and Project Number Request processes are performed through DelDOT’s Unifier software. DelDOT maintains many Unifier related instructions and tutorials on its [https://deldot.gov/Business/drc/index.shtml?dc=unifier Design Resource Center (DRC)] website. | |||
</p> | |||
<h2> | |||
3.4 Professional Services | |||
</h2> | |||
<p> | |||
The need for professional services should be considered by the Project Manager as early as feasible during the project initiation phase as their use will need to be factored into the project baselining activities described in [[Chapter 3 - Project Initiation#3.2.1 Initial Project Baselining|Section 3.2.1]]. Professional services can be used to perform specific portions or all the project design; additionally, professional services can be used to perform design support activities like site investigations. This section summarizes considerations for procuring and managing professional services. In all cases, the need for professional services should be evaluated on a project-by-project basis. | |||
</p> | |||
<div class="tab"> <!--h3--> | |||
<h3> | <h3> | ||
3.4.1 Professional Services Procurement | |||
</h3> | </h3> | ||
<table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | <table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | ||
| Line 436: | Line 247: | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>[https://deldot.gov/ | <td>[https://deldot.gov/Publications/manuals/professional_services/pdfs/ProfessionalServicesProcurementManual2016.pdf Professional Services Procurement Manual]</td> | ||
</tr> | </tr> | ||
</table> | </table> | ||
<p> | <p> | ||
DelDOT is required to maintain written procedures related to professional service procurement in accordance with both the Delaware Code and the Code of Federal Regulations (CFR). DelDOT’s written procedures for obtaining professional services is recorded in its [https://deldot.gov/Publications/manuals/professional_services/pdfs/ProfessionalServicesProcurementManual2016.pdf Professional Services Procurement Manual]. The manual establishes DelDOT’s procurement procedures and ensures compliance with the applicable federal and state regulations regarding professional service procurement which includes but is not limited to: [https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200 2 CFR 200], [https://www.ecfr.gov/current/title-2/subtitle-B/chapter-XII/part-1201 2 CFR 1201], [https://www.ecfr.gov/current/title-23/chapter-I 23 CFR 1-999], [https://www.ecfr.gov/current/title-49/subtitle-B/chapter-VI 49 CFR 600-699], and [https://delcode.delaware.gov/title29/c069/index.html 29 Chapter 69] of the Delaware Code. Accordingly, all professional service procurements must follow the requirements contained within DelDOT’s [https://deldot.gov/Publications/manuals/professional_services/pdfs/ProfessionalServicesProcurementManual2016.pdf Professional Services Procurement Manual]. | |||
</p> | </p> | ||
<p> | <p> | ||
Professional services can generally be divided into two categories with unique project level procurement considerations which are further discussed in [[Chapter 3 - Project Initiation#3.4.1.1 Design Related Professional Services|Section 3.4.1.1]] and [[Chapter 3 - Project Initiation#3.4.1.2 Design Support Related Professional Services|Section 3.4.1.2]]. Advanced FHWA approval is required in accordance with [https://www.ecfr.gov/current/title-23/chapter-I/subchapter-B/part-172 23 CFR 172.7(b)(5)] when Federal-aid funds participate in a contract to provide consultant services in a management role (such as managing a project or overseeing other consultants) relating to highway construction. All questions regarding professional procurement should be directed to DelDOT’s Consultant Control Coordinator. | |||
</p> | </p> | ||
<div class="tab"> <!--h4--> | <div class="tab"> <!--h4--> | ||
<h4> | <h4> | ||
3.4.1.1 Design Related Professional Services | |||
</h4> | </h4> | ||
<table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | <table class="wikitable" cellpadding="15" style="text-align:center;width: 45%;margin-left:auto;margin-right:auto;float:right"> | ||
| Line 481: | Line 266: | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>[https://deldot.gov/ | <td>[https://deldot.gov/Publications/manuals/professional_services/pdfs/ProfessionalServicesProcurementManual2016.pdf Professional Services Procurement Manual]</td> | ||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>[https://www.deldot.gov/Business/drc/forms/funding_increase_form.xlsx Funding Increase Request Form]</td> | |||
</tr> | </tr> | ||
<tr> | <tr> | ||
<td>[https://deldot.gov/ | <td>[https://deldot.gov/Business/drc/forms/transportation_solutions_funding_request.pdf?cache=1692186180259 Funding Request Form]</td> | ||
</tr> | </tr> | ||
</table> | </table> | ||
<p> | <p> | ||
Various sections throughout DelDOT advertise and award indefinite delivery/ indefinite quantity (IDIQ) project development contracts specifically for the performance of design work. IDIQ contracts are intended for performance of a number of routine or specialized tasks under a single professional service agreement. IDIQ contracts utilizing federal funds have a maximum contract period and a pre-set maximum dollar amount. As such, only services which fall within the advertised scope, funding, and schedule limitations of the established IDIQ contract may be awarded to one of the IDIQ selected consultants. IDIQ contracts are commonly referred to as open-end contracts. The federal requirements for IDIQ contracts are established in [https://www.ecfr.gov/current/title-23/chapter-I/subchapter-B/part-172 23 CFR 172.9(a)(3)]. | |||
</p> | </p> | ||
<p> | <p> | ||
Open-end contracts save time in the project development process by selecting several qualified firms that can provide the typical services required under an agreement thus eliminating the need to create, advertise, and award specific professional service agreements. Priority should be given to utilizing a firm on an established project development related professional services agreement for design work. If the appropriate expertise cannot be found under an established project development related professional services agreement or if the required work is determined too large for the professional service agreement, the Project Manager may elect to pursue the procurement of the desired professional service through a new and unique agreement in accordance with the DelDOT [https://deldot.gov/Publications/manuals/professional_services/pdfs/ProfessionalServicesProcurementManual2016.pdf Professional Services Procurement Manual]. It should be noted that it may take months to procure professional services when advertising a new and unique agreement. | |||
</p> | </p> | ||
<p> | <p> | ||
When using open-end agreements for the design work, the Project Manager must consider the contracted firms’ strengths, availability, qualifications, and overall ability to complete the task when determining the entity to assign the work to. Once the Project Manager determines the optimum firm to perform the work, they can request a draft scope of work and blank person-hour estimate from the selected contracted firm. The Project Manager should provide the selected firm with all the requisite information necessary for the firm to prepare an informed task proposal. The Project Manager should review the proposal upon receipt to ensure the scope of the work and tasks within the blank person-hour estimate are accurate and in-line with the Project Manager’s expectations. The Project Manager will communicate all comments on the draft scope of work and blank person-hour estimate to the consultant until all comments are sufficiently addressed. At this point, the Project Manager will prepare an independent person-hour estimate for the project that must be signed and dated. The consultant can then submit their person-hour estimate to the Project Manager who will then compare the estimates. The acceptability of the consultant’s proposal will be based on the following two guidelines: | |||
</p> | </p> | ||
< | <ol> | ||
<li> | |||
</ | For projects with a DelDOT estimate of less than 500 person-hours, if the consultant is within 15% of the DelDOT estimate (either above or below), the proposal will be acceptable. | ||
</li> | |||
<li> | |||
For projects with a DelDOT estimate of 500 person-hours or more, if the consultant is within 10% of the DelDOT estimate (either above or below), the proposal will be acceptable. | |||
</li> | |||
</ol> | |||
<p> | <p> | ||
If the differences between the consultant’s proposal and DelDOT’s independent person-hour estimate exceed these percentages (either above or below), a negotiation meeting should be held to resolve the differences. The negotiation meeting should result in a fair number of person-hours and the consultant should resubmit the proposal based on the negotiated hours. The documentation of the negotiation meeting should be saved within the project files. | |||
</p> | </p> | ||
<p> | <p> | ||
Once the task proposal is considered acceptable, the Project Manager will need to assess the project’s authorized funding to determine whether processing the consultant proposal will require additional authorized funding. When additional funds are required, the Project Manager will need to complete and submit the [https://www.deldot.gov/Business/drc/forms/funding_increase_form.xlsx Funding Increase Request Form] as further described [[Chapter 5 -Stakeholder Coordination|Section 5.8.1 (To be added)]]. Once the project’s authorized funding has been assessed and the necessary steps performed, the Project Manager can submit the proposal and a completed [https://deldot.gov/Business/drc/forms/transportation_solutions_funding_request.pdf?cache=1692186180259 Funding Request Form] to the appropriate Department mailboxes as shown in Table 3.4.1.1 for processing. The Project Manager should also attach the funding increase request email to the funding request email in cases where additional authorized funds were required to expedite the process. The subject line of the email sent to Department mailboxes shown in Table 3.4.1.1 should be the Agreement number, task number, and then supplemental number if applicable. The body of the email submitted should include the following text: “The attached proposal has been reviewed and found acceptable. Please proceed with the NTP process”. For DelDOT’s Traffic section, these funding assessment and processing activities are delegated by the Project Manager to Traffic’s Support Services section. | |||
</p> | </p> | ||
<label style="font-weight: bold;">Table 3.4.1.1 – Department Mailboxes for Proposal Processing</label> | |||
<table class="wikitable" cellpadding="15" style="text-align:center;width: 90%;margin-left:auto;margin-right:auto;"> | |||
<caption style="caption-side:bottom;font-size: 12px;text-align: left;"></caption> | |||
<tr> | |||
<th style="color:white;background-color:navy;font-weight: bold;text-transform: uppercase;"><b>Department Mailbox</b></th> | |||
<th style="color:white;background-color:navy;font-weight: bold;text-transform: uppercase;"><b>When to Include on Funding Request Email</b>></th> | |||
</tr> | |||
<tr> | |||
<td>[mailto:Dot.AuditManagement@delaware.gov DOT.AuditManagement@Delaware.gov] </td> | |||
<td>Include on all Funding Requests | |||
</td> | |||
</tr> | |||
<tr> | |||
<td>[https://www.deldot.gov/Business/drc/forms/funding_increase_form.xlsx Funding Increase Request Form]</td> | |||
<td>[https://www.deldot.gov/Business/drc/forms/funding_increase_form.xlsx Funding Increase Request Form]</td> | |||
</tr> | |||
<tr> | |||
<td>[https://deldot.gov/Business/drc/forms/transportation_solutions_funding_request.pdf?cache=1692186180259 Funding Request Form]</td> | |||
<td>[https://deldot.gov/Business/drc/forms/transportation_solutions_funding_request.pdf?cache=1692186180259 Funding Request Form]</td> | |||
</tr> | |||
</table> | |||
</div> | </div> | ||
</div> <!--end of h3--> | |||
</div> <!--end of h2--> | |||
</div><!-- | |||
</div> <!-- | |||
Revision as of 17:27, 5 April 2024
Chapter 3 - Project Initiation
After a project is originated in accordance with one of the mechanisms described in Chapter 2, it is assigned to a section within DelDOT for further development. This stage in the project development process is generally referred to as project initiation. This chapter serves to document the numerous tasks that a section must perform as part of the project initiation process once assigned a project. Project initiation is a relatively short phase in the project development process but serves an essential role of establishing an initial project baseline to follow through the remainder of the project development process. The activities described within this chapter can be performed in various orders depending on the complexity of a project. For instance, it may be preferrable to perform a detailed scoping and alternatives analysis prior to setting a project schedule while on other projects it may be preferable to account for the scoping and alternatives analysis within the initial project schedule submitted with the Project Number Request.
3.1 Establishment of the Design Team
The section assigned to develop a project should establish a design team comprised of a Project Manager and technical design staff as soon as practical. Collectively, the design team is charged with guiding a project through DelDOT’s project development process outlined within this manual. The Project Manager’s role in the project development process is to coordinate technical design staff assignments and ensure that all work is being completed at the correct performance level, on time, and within budget and scope. The technical design staff’s role in the project development process is to perform the tasks assigned to them by the Project Manager in accordance with this manual as well as other DelDOT standard and guidance documents. The Project Manager should evaluate the composition of the team at regular intervals throughout the project development process to ensure on-time and on-budget delivery.
In general, projects can either be developed through in-house staff or can be developed in-whole or in-part by contracted consultant staff through professional service agreements. The Project Manager should consider multiple factors when establishing the design team, including but not limited to, the following:
- Availability of in-house staff,
- Expertise and experience required to perform project related tasks,
- Desired implementation schedule, and
- Available funding.
The procurement and subsequent management of professional services is further discussed in Section 3.4 of this manual.
3.1.1 Support Groups
The design team’s efforts are supplemented by Support Groups throughout DelDOT. Support Groups typically oversee a particular area of the of the project development process and perform ancillary tasks to deliver a project. Support Groups are relied upon by DelDOT as subject matter experts within their field due to their focus and expertise on a particular subject matter within the project development process. The process established in this manual is intended to leverage the expertise and experience of DelDOT’s of subject matter experts in order to develop complete, accurate, and thorough project deliverables which meet the applicable state and federal requirements. Coordination with subject matter experts is typically triggered by milestone submittals which are discussed in more detail in Section 6.3; however, communication and coordination with DelDOT subject matter experts should occur fluidly throughout the project development process as needs arise. Early and consistent communication throughout the project development process will promote informed decision-making, reduce duplicated efforts amongst staff, and allow early identification and subsequent remediation of challenges that could jeopardize project delivery.
3.2 Project Baselining
Project baselining is the term assigned to the task of evaluating a project’s specific conditions, parameters, and other associated constraints to determine an estimated project schedule and budget. A project is baselined during the project initiation phase and will typically be re-baselined several times throughout the full project development process. The design team should collaborate with support sections as needed while performing this task to ensure the development of accurate project baselines. Accurate project baselining is essential to the development of a fiscally constrained program to make efficient use of transportation funds.
3.2.1 Initial Project Baselining
Once assigned a project, the assigned section must review the project’s proposed scope and any associated planning and study level documents to create a project schedule, budget, and an initial environmental evaluation. In cases where the project scope and goals are unclear, additional project scoping and alternatives analysis may be performed before establishing the project’s initial baseline. Some projects may come with a previously developed schedule and budget depending upon the program generating the project; in these cases, the design team should evaluate the validity of any previously developed schedules and budgets before formally committing to any previously developed project baselines.
The design team should evaluate the project at this initial baselining stage to determine if an alternative project delivery or alternative contracting method should be pursued for the project. Additional information on the available contracting and project delivery methods are provided in Section 6.1.
At a minimum, the assigned section should make a concerted project scoping effort to identify the key project stakeholders as well as other specific conditions or parameters that could affect the project development process while developing the initial baseline. Additional information on project scoping is included in Section 3.6.
3.2.1.1 Schedule
Project scheduling requires the identification of all necessary work activities, development of work-hour estimates for work activities, and then defining relationships between the work activities to produce the project desired deliverables. The Project Manager is tasked with either verifying a previously developed project schedule or developing a new project development schedule as part of the project initiation process. The initial project development schedule will need to identify the proposed completion month for all milestone project development deliverables. DelDOT’s typical milestone deliverables are discussed in more detail in Section 6.3. The Project Manager is encouraged to use scheduling tools commensurate with the project’s complexity to assist in the development of the initial project schedule. Project scheduling tools can range from a simple Excel spreadsheet to a complex scheduling software that assigns task durations and analyzes critical paths.
The Project Manager should consider all project specific criteria when developing the initial project schedule. Considerations include, but are not limited to, the following:
- The potential use of any contracting methods as discussed in Section 6.1,
- Availability of the assigned design team,
- Experience and associated capability of the assembled design team,
- Complexity of the project,
- The number and type of desired milestone submittals and deliverables,
- Identification of any critical project milestone dates,
- Time needed for initial site investigation,
- Time needed for any necessary property acquisitions or trespass/ rail agreements,
- Time needed to satisfy pertinent environmental requirements (i.e. permitting, wetland mitigation, 106 compliance, NEPA compliance etc.), and
- Any publicly committed completion timeframes.
3.2.1.2 Budget
Accurately establishing the budget during the project initiation phase is essential to ensuring a fiscally responsible program and proper project funding. Overestimating the budget will lead to surplus funds being withheld from other infrastructure projects and underestimating the budget could lead to schedule disruptions. A project may be assigned to a section either with or without an already estimated budget depending upon the mechanism generating the project. Whether or not the project is assigned with a pre-estimated budget, the Project Manager and the design team should perform a project cost estimate for the design phase, the right-of-way acquisition, and construction phase which is commensurate with the project’s complexity and overall size. Additional information on cost estimating is included within Section 6.5. In all cases, the project’s budget during this stage in the project development process is to be recorded into the following funding phases:
- Preliminary Engineering (PE, includes all design related work required to get the project through the advertisement phase),
- Right-of-Way (RW), and
- Construction (C, includes any construction contingency, environmental monitoring during construction, railroad construction, traffic construction, reimbursable utility construction, and construction engineering (CE) costs).
Items the Project Manager should consider while developing the initial project budget, include but is not limited to, the following:
- Professional services required to perform existing site investigation activities discussed in Section 3.7,
- Professional services required to perform project design,
- Professional services required to perform any ancillary tasks required to deliver a project (i.e. utility coordination, public outreach, environmental permitting etc.),
- The expected cost of any right-of-way acquisitions that may be required, and
- The expected cost of all necessary construction and inspection activities.
Another important item to establish is whether the project will receive federal funding during any project funding phase. This will typically be a joint decision between the design team and the Finance section. It is important to note that once federal funds are used in any funding phase that all previous work performed must meet the pertinent federal requirements.
Projects assigned with a pre-estimated budget listed in the Capital Transportation Plan CTP may require a funding increase when determined the dedicated funding is insufficient. Additional information on funding increases is provided in Section 5.8.1 (To be added).
3.2.1.3 Initial Environmental Evaluation
The Project Manager should request an initial environmental evaluation from the DelDOT Environmental Stewardship section as part of a project’s initial baselining. The initial environmental evaluation serves to inform the Project Manager and the design team of the environmental coordination related processes and deliverables which will need to be accounted for during their initial baselining effort. To obtain an initial environmental evaluation, the design team will need to complete the Initial Environmental Evaluation Form and submit it to the Environmental Stewardship section. The Environmental Stewardship section will review the information provided by the design team and complete the remainder of the form. The Environmental Stewardship section will submit the completed form back to the design team and will request that the design team attend the next Environmental Stewardship section group meeting, commonly referred to as the ESO meeting, to discuss the content of the initial environmental evaluation as well as the division of work between the design team and the Environmental Stewardship section. The Environmental Stewardship section may contact the Federal Highway Administration (FHWA), or other federal administering agency, in accordance with 23 CFR 771.111(a)(3) to obtain advice, insofar as possible, on the probable class of action and related environmental laws and requirements and of the need for specific studies and findings that would normally be developed during the environmental review process. At a minimum, the initial environmental evaluation will provide the following:
| Department Resources | |||
|---|---|---|---|
| Initial Environmental Evaluation Form | |||
- The initial level of environmental documentation and class determination,
- Identification of design/project development considerations, including but not limited to, historic properties and structures, archaeological sites, tribal coordination requirements, Section 4(f) and 6(f) properties, wetlands and waterbodies, endangered species, and environmental justice (EJ),
- An initial public involvement strategy requirement, and
- Funding needs and task assignments.
3.2.2 Project Re-Baselining
A project’s schedule and budget should be re-baselined throughout the project development process to ensure the efficient use of DelDOT resources and to minimize the potential for creating duplicate work products. Projects are typically re-baselined at the milestone submissions described in Section 6.3 and should also be re-baselined when major changes within the project development process occur such as a change in the project team occurs or when previously unanticipated work and coordination efforts become required. Reference should be made to [[Chapter 5 - Stakeholder Coordination|Section 5.8.1 (To be added)] when re-baselining reveals the project has insufficient fund.
3.2.2.1 Re-Baselining at Milestone Submissions
| Department Resources | |||
|---|---|---|---|
| Unifier Training Outline | |||
| Youtube Tutorial Video | |||
A project’s schedule and budget are to be updated in Unifier at each milestone submission to communicate a project’s current estimated budget and schedule to the rest of DelDOT. The project’s schedule and budget can be estimated using the same considerations as the initial project baselining effort described in Section 3.2.1. DelDOT maintains written procedures for updating a project’s information in its Unifier Training Outline and maintains a tutorial video on the subject on its Youtube channel.
3.2.2.2 Spend Updates
A spend plan that outlines when the project team estimates money will be spent throughout the project development process is created as part of the procedure outlined in Section 3.2.1. Periodically throughout the course of the project development process, the Project Manager will review the actual rate of project expenditures compared to the expected expenditure rate in order to evaluate the accuracy of the spend plan. After their review, the Project Manager can recommend that money be moved up in the spend plan or moved back. This practice of reviewing and making recommendations on project funding to the DelDOT Finance team is known as making spend updates. DelDOT sections typically use different spend update intervals based on the amount, complexity, typical schedule, and budget of projects being managed by the section. Conducting spend updates also provides a good opportunity for the Project Manager to review the project’s overall budget to determine if the project will require additional funding or if the project has a surplus amount of funds allotted.
3.3 Project Number Request
| Department Resources | |||
|---|---|---|---|
| Unifier Instructions on the DRC | |||
Once the initial project baselining is complete, a New Project Request and subsequent Project Number Request can be performed. DelDOT assigns a state project number and a federal project number, when necessary, to its projects to assist with project identification and tracking. The New Project Request and Project Number Request processes are performed through DelDOT’s Unifier software. DelDOT maintains many Unifier related instructions and tutorials on its Design Resource Center (DRC) website.
3.4 Professional Services
The need for professional services should be considered by the Project Manager as early as feasible during the project initiation phase as their use will need to be factored into the project baselining activities described in Section 3.2.1. Professional services can be used to perform specific portions or all the project design; additionally, professional services can be used to perform design support activities like site investigations. This section summarizes considerations for procuring and managing professional services. In all cases, the need for professional services should be evaluated on a project-by-project basis.
3.4.1 Professional Services Procurement
| Department Resources | |||
|---|---|---|---|
| Professional Services Procurement Manual | |||
DelDOT is required to maintain written procedures related to professional service procurement in accordance with both the Delaware Code and the Code of Federal Regulations (CFR). DelDOT’s written procedures for obtaining professional services is recorded in its Professional Services Procurement Manual. The manual establishes DelDOT’s procurement procedures and ensures compliance with the applicable federal and state regulations regarding professional service procurement which includes but is not limited to: 2 CFR 200, 2 CFR 1201, 23 CFR 1-999, 49 CFR 600-699, and 29 Chapter 69 of the Delaware Code. Accordingly, all professional service procurements must follow the requirements contained within DelDOT’s Professional Services Procurement Manual.
Professional services can generally be divided into two categories with unique project level procurement considerations which are further discussed in Section 3.4.1.1 and Section 3.4.1.2. Advanced FHWA approval is required in accordance with 23 CFR 172.7(b)(5) when Federal-aid funds participate in a contract to provide consultant services in a management role (such as managing a project or overseeing other consultants) relating to highway construction. All questions regarding professional procurement should be directed to DelDOT’s Consultant Control Coordinator.
3.4.1.1 Design Related Professional Services
| Department Resources | |||
|---|---|---|---|
| Professional Services Procurement Manual | |||
| Funding Increase Request Form | |||
| Funding Request Form | |||
Various sections throughout DelDOT advertise and award indefinite delivery/ indefinite quantity (IDIQ) project development contracts specifically for the performance of design work. IDIQ contracts are intended for performance of a number of routine or specialized tasks under a single professional service agreement. IDIQ contracts utilizing federal funds have a maximum contract period and a pre-set maximum dollar amount. As such, only services which fall within the advertised scope, funding, and schedule limitations of the established IDIQ contract may be awarded to one of the IDIQ selected consultants. IDIQ contracts are commonly referred to as open-end contracts. The federal requirements for IDIQ contracts are established in 23 CFR 172.9(a)(3).
Open-end contracts save time in the project development process by selecting several qualified firms that can provide the typical services required under an agreement thus eliminating the need to create, advertise, and award specific professional service agreements. Priority should be given to utilizing a firm on an established project development related professional services agreement for design work. If the appropriate expertise cannot be found under an established project development related professional services agreement or if the required work is determined too large for the professional service agreement, the Project Manager may elect to pursue the procurement of the desired professional service through a new and unique agreement in accordance with the DelDOT Professional Services Procurement Manual. It should be noted that it may take months to procure professional services when advertising a new and unique agreement.
When using open-end agreements for the design work, the Project Manager must consider the contracted firms’ strengths, availability, qualifications, and overall ability to complete the task when determining the entity to assign the work to. Once the Project Manager determines the optimum firm to perform the work, they can request a draft scope of work and blank person-hour estimate from the selected contracted firm. The Project Manager should provide the selected firm with all the requisite information necessary for the firm to prepare an informed task proposal. The Project Manager should review the proposal upon receipt to ensure the scope of the work and tasks within the blank person-hour estimate are accurate and in-line with the Project Manager’s expectations. The Project Manager will communicate all comments on the draft scope of work and blank person-hour estimate to the consultant until all comments are sufficiently addressed. At this point, the Project Manager will prepare an independent person-hour estimate for the project that must be signed and dated. The consultant can then submit their person-hour estimate to the Project Manager who will then compare the estimates. The acceptability of the consultant’s proposal will be based on the following two guidelines:
- For projects with a DelDOT estimate of less than 500 person-hours, if the consultant is within 15% of the DelDOT estimate (either above or below), the proposal will be acceptable.
- For projects with a DelDOT estimate of 500 person-hours or more, if the consultant is within 10% of the DelDOT estimate (either above or below), the proposal will be acceptable.
If the differences between the consultant’s proposal and DelDOT’s independent person-hour estimate exceed these percentages (either above or below), a negotiation meeting should be held to resolve the differences. The negotiation meeting should result in a fair number of person-hours and the consultant should resubmit the proposal based on the negotiated hours. The documentation of the negotiation meeting should be saved within the project files.
Once the task proposal is considered acceptable, the Project Manager will need to assess the project’s authorized funding to determine whether processing the consultant proposal will require additional authorized funding. When additional funds are required, the Project Manager will need to complete and submit the Funding Increase Request Form as further described Section 5.8.1 (To be added). Once the project’s authorized funding has been assessed and the necessary steps performed, the Project Manager can submit the proposal and a completed Funding Request Form to the appropriate Department mailboxes as shown in Table 3.4.1.1 for processing. The Project Manager should also attach the funding increase request email to the funding request email in cases where additional authorized funds were required to expedite the process. The subject line of the email sent to Department mailboxes shown in Table 3.4.1.1 should be the Agreement number, task number, and then supplemental number if applicable. The body of the email submitted should include the following text: “The attached proposal has been reviewed and found acceptable. Please proceed with the NTP process”. For DelDOT’s Traffic section, these funding assessment and processing activities are delegated by the Project Manager to Traffic’s Support Services section.
<label style="font-weight: bold;">Table 3.4.1.1 – Department Mailboxes for Proposal Processing</label>
| Department Mailbox | When to Include on Funding Request Email> |
|---|---|
| DOT.AuditManagement@Delaware.gov | Include on all Funding Requests |
| Funding Increase Request Form | Funding Increase Request Form |
| Funding Request Form | Funding Request Form |